Subject: How to Import the SWMM 5 Report File as a Layer in infoSWMM
The idea of this blog of note is to show how one may extract information from the SWMM 5 or InfoSWMM RPT file and import the Excel File as a feature in InfoSWMM. This blog has an example Excel file to illustrate the linkage. The steps are:
Step 1: Copy the whole row from Conduit Summary from the InfoSWMM Browser
Step 2: Add the two columns length and slope from the Link Summary Table and the InfoSWMM Browser
Step 3: You need a few calculations based on the table values from SWMM 5 to estimate the CFL time steps in the .
Step 4: Add the Excel Spreadsheet as a layer in InfoSWMM – the Named Rangeshould be added to insure valid numbers and not Nulls after the join
Step 5: You can now plot the CFL Time Step for the Links using the Layer Properties command in Arc Map
Step 1: Copy the whole row from Conduit Summary
Step 2: Add the two columns length and slope from the Link Summary Table
Step 3: You need a few calculations based on the table values from SWMM 5 to estimate the CFL time steps.
The CFL Step = Length / (Full Velocity + (Gravity * Full Depth)^0.5)
Full Velocity = Full Flow / Full Area
You also need to create a Name A Range for you data so that the data does not show up as Nulls
Step 4: Add the Excel Spreadsheet as a layer in InfoSWMM – the Named Range should be added
Step 4: Join the Excel Table to the InfoSWMM Conduit Feature Layer
Step 5: You can now plot the CFL Time Step for the Links using the Layer Properties command in Arc Map
|
Autodesk Technologist with Information about Stormwater Management Model (SWMM) for watershed water quality, hydrology and hydraulics modelers (Note this blog is not associated with the EPA). You will find Blog Posts on the Subjects of SWMM5, ICM SWMM, ICM InfoWorks, InfoSWMM and InfoSewer.
Saturday, February 4, 2012
How to Import the SWMM 5 Report File as a Layer in infoSWMM
Subscribe to:
Post Comments (Atom)
Today is day 356 or 97.5 percent of the year 2024
English: Today is day 356 or 97.5 percent of the year 2024 Mandarin Chinese: 今天是2024年的第356天,即97.5% Hindi: आज 2024 का 356वां दिन या 97.5 प्रत...
-
@Innovyze User forum where you can ask questions about our Water and Wastewater Products http://t.co/dwgCOo3fSP pic.twitter.com/R0QKG2dv...
-
Subject: Detention Basin Basics in SWMM 5 What are the basic elements of a detention pond in SWMM 5? They are common in our back...
-
Soffit Level ( pipe technology ) The top point of the inside open section of a pipe or box conduit. The soffit is the ...
No comments:
Post a Comment